特级黄一区二区三区_超碰97在线免费看_久久久久亚洲av成人网人人软件_中国高清一级黄色A片_日韩无码久久亚洲AV爱爱_国产色精品Av久久人妻无码_欧美国产日韩第一页_一级了片黄色国产在线第九页

News
Wanshun dynamic real-time  , thank you for your attention and support!
Location:Home> News> Company news

Wanshun Chemical - Environmental Information Disclosure (2018)
2018-07-30 00:00:00

Nantong Wanshun Chemical Technology Co., LTD

Environmental information disclosure content

According to the requirements of the Ministry of Environmental Protection Decree No. 31 "Measures for the Disclosure of Environmental Information of Enterprises and Institutions", the company's environmental information for this year is now disclosed as follows:

1. Basic information:


ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

2, sewage information:

Since the company was built and put into operation, the data of waste water and waste gas have qualified, and the total amount control has been strictly implemented. The company has passed the 2016 project acceptance test and met the discharge standards in each annual test. The quarterly monitoring data of 2017 is publicized as follows:

2.1 Waste water

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

2.2 Exhaust Gas

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

     

(3) Construction and operation of pollution prevention facilities

3.1 Wastewater treatment facilities:

The wastewater treatment facilities of our company were commissioned by Nanjing Industrial Environmental Technology Co., LTD., with a designed treatment capacity of 340 tons/day, which was put into use in June 2015. In the operation process of more than two years, the wastewater treatment facilities can be stable operation, and the wastewater is stable and discharged up to the standard.

3.1.1 Waste water collection: The process waste water of the resin workshop and the recycling workshop shall be sent directly to the comprehensive regulating tank of the waste water treatment post through the open pipe; The plant is equipped with initial rainwater collection tank, domestic sewage collection tank, accident waste water collection tank; Workshop emergency pools are provided in each workshop.

3.1.2 Our company conducts classified collection and qualitative treatment of wastewater. Low-concentration wastewater, such as initial rainwater and domestic sewage, is transported to the comprehensive regulation tank of wastewater treatment posts; The accident water is transported to the alkaline hydrolysis tank at the wastewater treatment post for alkaline hydrolysis first, and is now sent to the comprehensive regulation tank.

3.1.3 After the wastewater from the comprehensive regulation tank is pumped to the anaerobic tank with the lift, it passes the two-stage A/O treatment (anaerobic tank + aerobic A section + anaerobic tank + aerobic B section) and then discharged to the park sewage treatment plant to meet the standard.

3.1.4 The company has built an online monitoring room at the tail pond to conduct real-time online monitoring and analysis of COD, and network with the environmental protection system of the park. Meanwhile, Jiangsu Tianze Environmental Protection Co., Ltd. is entrusted to operate and maintain the online monitoring system. The operation ledger and operation and maintenance ledger of wastewater treatment facilities are complete with real data.

3.1.5 The company has set up an environmental protection department, which is responsible for the operation of wastewater treatment posts and equipped with professional operators. The treatment capacity at each stage has reached the design target and the operation is in good condition. In the company's daily monitoring and completion acceptance monitoring, annual environmental monitoring process, all drainage indicators are up to standard and in line with the total environmental assessment control indicators, the company's drainage indicators are qualified.

3.2 Waste gas treatment facilities and operation status

3.2.1 The waste gas treatment facilities of our company were designed by Jiangsu Nanda Environmental Protection Technology Co., LTD., and put into use in June 2015. In the operation process of more than two years, the waste gas treatment facilities can run stably, and the exhaust gas is stable and discharged up to the standard.

3.2.2 Waste gas treatment process

Resin workshop: solvent gas (process waste gas) in the production process is recovered by condensation first. The unorganized exhaust gas is first collected by the sealed pipe, and enters the exhaust gas treatment system together with the process exhaust gas. After the treatment of two-stage water absorption + first-stage activated carbon adsorption, it is discharged through the 15-meter chimney to meet the standard.

Recovery workshop: Process exhaust gas and vacuum pump exhaust gas from the production process are collected into a exhaust pipe and enter the exhaust gas treatment system. Formic acid, dimethylamine and DMF in the exhaust gas are treated by two-stage falling film absorption + two-stage dilute hydrochloric acid absorption method. The treated gas is merged into the 15-meter chimney of the resin workshop and discharged to the standard.

Waste water treatment station: Solid waste warehouse and waste water pool are sealed and collected, then subjected to first-level water absorption + first-level dilute acid absorption treatment, and discharged up to standard through a 15-meter chimney.

3.2.3 Our company's waste gas treatment facilities are in place and run stably and effectively in accordance with the EIA requirements and design scheme. The operation of exhaust gas facilities is included in the daily workshop management work, and the responsibility for touring and maintenance is implemented. The PH online monitor is installed in the four-stage absorption tower of the recycling post, and the PH online monitor is also installed in the tail gas acid absorption tower of the wastewater treatment post. Each absorption tower is equipped with sight mirror to observe the spray of absorption liquid in time; Replace each acid and base absorption solution according to PH value, and replace each water absorption solution regularly.

3.2.4 In the daily supervision, our company installed the advanced VOC online detection instrument in the exhaust emission outlet of the production workshop, real-time monitoring of the exhaust emission concentration of the production workshop. The daily company monitoring and outsourcing monitoring of pollutant emission data are qualified and up to the standard, and all pollution factors are in line with the total amount approved by the environmental assessment.

3.3 Solid waste treatment

3.3.1 All hazardous waste generated by the company is temporarily stored in hazardous waste storage, and a hazardous waste warehouse of 144㎡ has been built in accordance with the "eight prevention" requirements of solid waste facilities. Diversion ditch, leachate collection tank, ground anti-corrosion, fire fighting facilities, etc., have been built in place. The generated solid waste is uniformly entrusted by the Environmental Protection Department to Rudong Daheng Hazardous Waste Treatment Co., LTD for disposal.

3.3.2 The general solid waste generated in the production of the project is domestic waste, which will be uniformly collected by Rudong Xintiandi Property Company and transported and disposed of.

3.4 Noise Control

In terms of noise control, our company can maximize the control of noise through acoustic rooms, shock pads, silencers, soft connections and other auxiliary measures, while using new fans to reduce the contribution of noise to the environment. In terms of management, it is necessary to strengthen post tour and increase equipment maintenance to ensure the stable operation of various pumps, fans and other equipment. After taking the above control measures, it is ensured that all the factory boundary noise meets the Class 3 standard of the Industrial Enterprise Factory Boundary Ambient Noise Emission Standard (GB12348-2008) (i.e. less than 65dB(A) during the day and less than 55dB(A) during the night).

3.5 Exhaust gas online monitoring operation and maintenance contract

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

hFYF8BK8TjCDBV_egqT48w.png

4. Administrative approval of construction projects

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

5. Emergency plan for sudden environmental events

On April 17, 2015, the "Emergency Plan for Environmental Emergencies" prepared by our company passed the record of Rudong County Environmental Protection Bureau, the record number: 320623-2015-025-H. At present, the record of the plan has expired, combined with the transformation of DMF recycling posts, our company has carried out a retrospective environmental assessment, and the report has been submitted for review; At the same time, the emergency plan has been prepared according to the new environmental assessment, combined with the internal situation of the enterprise, in accordance with the requirements of the new guidelines, and after the approval of the new environmental assessment, the plan can be reviewed and filed.

ccd2ff11-d26e-40aa-8165-c41e26aa3dc0.jpg

In accordance with the requirements of the plan, the company carries out emergency training every year, and conducts two emergency plan drills to improve the emergency handling ability of all personnel for unexpected events.

6.1 EIA approval


6.2 Opinions on pilot production


6.3 Project completion acceptance opinions

The company has always adhered to the principle of safe development and environmental protection priority, and continuously increased investment in environmental protection, while taking process management as an important starting point, effectively promoting clean production, ensuring the stable discharge of waste water and waste gas up to standard, and ensuring the standardized disposal of hazardous waste.

Our company voluntarily discloses corporate environmental protection related information and accepts social supervision.

Nantong Wanshun Chemical Technology Co., LTD

April 25, 2018


主站蜘蛛池模板: 半推半就人妻一区| 欧美一区二区高清视频| 强奸少妇黄片免费伊人av| 日韩和亚洲av日韩激情网| 找黄色一练毛片午夜熟女| 欧美美女A级视频| 黄色毛片视频网站免费提供| 不要播放器AV网站| 日韩日韩日韩日韩日韩| 人妻性爱在线A逼毛片视频| 免费无码一级片,动漫| 亚洲图区,综合一区| 婷婷色播五月激情| 国内高清无码91| 国产美女黄网站免| 国内自拍露脸性爱视频在线观看| 黄色A片三级片在线观看| 91久久国产综合久久91精品在线| 极品无码三级AV| 日本黄色视频在线网址| 三级黄色视频a在线性爱| 婷婷五月天中文字幕| AV无码一区在线观看| 1区2区av成人av国产| 日韩欧美无卡视频| 91wwwxxx| 久草aV电影黄色a一级| 高清成人电影A片视频网站| 丰满美女免费黄色毛片| 中文字幕熟女人妻色情片在线播放| 久久国产精品在线播放| 国产视频不卡国产精品视频| 精品无码av无码专区| 亚洲国产精品配视频| 人人曰人人曰人人| 精品无码国产污污污免费网站久久| 国产精品观看黄色影视大全| 综合国产无码精品无马| 综合社区在线一区二区自拍视频| www岛国成人深夜无码高清| 黄色一级片插叉插有爽的|